Current Roadway Construction and Maintenance

This page will be updated as projects are added.  Start/Completion dates are for general reference only and are subject to change.

SP 136 Rustlers Gulch Equestrian Trail

Construct 2.25 miles of non-motorized trail within the right of way.

Construction planned fall of 2017

Design
Construction
CRP 824 Fertile Valley Rd

Re-Construct 2.5 miles of County Road From State Hwy 211 to the Outlet Bridge.
Projected start date of July 9th, 2018

Design
Construction
CRP 837 Sullivan Lake Rd MP 8.3

Replacement of the Sullivan Lake Inlet Bridge.

Contractor: Versatile Industries Inc- Ione, WA

Construction Completed

Design
Construction
CAPP 2018

CAPP 2018 Pavement Preservation. Only paver patching scheduled this season.

Design
Construction
Striping Program

Centerline and edge striping, stop bars and cross walk striping.

Design
Construction
SP-121 Leclerc Rd S MP 6.25 Indian Creek Fish Passage

Construction underway Contractor-NA Degestrom

Design
Construction
CRP-839 Leclerc Rd South Intersection Improvement with Sandy Shores Rd

Construction planning on hold. Currently in R.O.W. and permitting phase.

Design
Construction
2018 Gravel Road Stabilization Program

Includes calcium chloride and magnesium chloride treatments for stabilization of at risk road segments. Project completed spring of 2018

Design
Construction
2018 Right of Way Vegetation Control Program

Starting Spring through Fall 2018. Work includes spraying, shoulder mowing and brush cutting. Land owners may opt out for spraying, please see our Vegetation Control page. Work is County wide.

Design
Field Work
2018 Bridge Inspection Program

Includes bi-annual inspections of County owned structures. Inspection of the Usk Bridge is scheduled.

Design
Field Work