SP 121

Replacement of the Indian Creek Crossing on Leclerc Rd South

PUBLIC NOTICE

Paving scheduled for 9/24/2018. Removal of existing pipe to follow.

Don Ramsey, P.E.

Project Engineer

George W. Luft

Design Engineer, Project Lead

Eric M. Roth, P.L.S.

Project Surveyor
  • Email

    publicworks4u@pendoreille.org

  • Phone

    509-447-4513

  • In Person

    625 W. 4th St. Newport, WA

 

Partners- WSDOT  Highways & Local Programs(Support Services)

Federal Highways($1,700,000.00)

Washington State Salmon Recovery Funding Board($250,000)

Kalispel Tribe of Indians(Land Donation & Steering, Access)

County Contribution (Unknown at this point)

Anticipated Project Start-Spring 2018

Anticipated Project Completion-Fall of 2018

Project Timeline

  • Preliminary Design Concept
    Originally planned to be part of Phase III of the Leclerc South Cooridor Improvement
  • Design Funding Awards
    Design-2010
  • Field Surveying of project limits
    Fall 2011
  • Preliminary Design
    Winter 2011
  • Field Stake Proposed Alignment
    Spring Of 2015
  • Construction Funding Award
    2015
  • Project Bid
    Bids were opened in late fall of 2017.  NA Degestrom was awarded the contract.
  • Project begins
    The contractor did some exploratory excavation this week and began to mobilize equipment to the site.
  • Paving Scheduled
    9/24/2018